CIV E 638 -
SEDIMENTATION AND RIVER ENGINEERING
FALL 2020
HOMEWORK No. 3: CHANNEL MORPHOLOGY
-
Use the Modified Lane method to calculate the sediment discharge Qs in metric tons per day, given the
following hydraulic and sedimentological data: discharge Qw = 1 m3/s; bottom slope So = 0.001; hydraulic radius R = 1 m;
particle size ds = 1 mm.
Assume k1 = 0.01. Confirm with ONLINE MODIFIED LANE.
- Use the Modified Lane method
to calculate the sediment discharge Qs in tons per day, given the
following hydraulic and sedimentological data: discharge Qw = 100 cfs; bottom slope So = 0.002; hydraulic radius R = 1 ft; particle size ds = 0.8 mm.
Assume the default k1 = 0.001. Confirm with ONLINE MODIFIED LANE.
- For the data of Problem 1, assume that a sediment retention basin retains 50% of the sediment discharge
and the representative particle size downstream of the retention basin reduces to ds = 0.7 mm. According to the Modified Lane relation, what is the prevailing downstream slope So,2 produced
by degradation?
- For the data of Problem 3, what downstream slope would be predicted by the Lane relation?
|